Report 2022-301 Recommendation 8 Responses
Report 2022-301: Judicial Branch Procurement: Although Four Superior Courts We Reviewed Generally Met Procurement Requirements, Glenn County Superior Court Needs to Significantly Improve Its Procurement Practices (Release Date: January 2023)
Recommendation #8 To: Superior Court of California, County of Glenn
To demonstrate that it follows competitive bidding and contract award requirements, Glenn should, by July 2023, develop and implement a process for ensuring that its contracting practices meet requirements in state law. The court should also maintain complete information and documentation about its population of contracts.
60-Day Agency Response
Glenn Court is currently working on a policy to address this concern.
- Estimated Completion Date: 6/1/2023
- Response Date: March 2023
California State Auditor's Assessment of 60-Day Status: Pending
All Recommendations in 2022-301
Agency responses received are posted verbatim.