Report 2022-115 Recommendation 1 Responses

Report 2022-115: Electricity and Natural Gas Rates: The California Public Utilities Commission and Cal Advocates Can Better Ensure That Rate Increases Are Necessary (Release Date: August 2023)

Recommendation #1 To: Public Utilities Commission

To promote transparency, the CPUC should by February 2024 institute a process that requires utilities to periodically publish actual rate-of-return calculations, using a methodology acceptable to the CPUC and to Cal Advocates.

60-Day Agency Response

The CPUC is establishing a process to require utilities to periodically publish actual rate-of-return calculations using a methodology acceptable to the CPUC and Cal Advocates. Developing this process requires internal consultation among staff and may result in the creation of a written procedure.

California State Auditor's Assessment of 60-Day Status: Pending


All Recommendations in 2022-115

Agency responses received are posted verbatim.