Report 2014-135R Recommendation 8 Responses

Report 2014-135R: Magnolia Science Academies: Although the Financial Condition of These Charter Schools Has Improved, Their Financial Controls Still Need to Be Strengthened (Release Date: May 2015)

Recommendation #8 To: Magnolia Educational and Research Foundation

To increase transparency and reduce the risk of misuse of funds, the Foundation should update its policies and procedures regarding vendor selection to require that it maintain independence in its relationships with vendors.

1-Year Agency Response

Magnolia Public Schools (MPS) has increased transparency by including a conflict of interest policy, acceptance of gratuities disclosures, and disciplinary actions. MPS is including the Board approved policies and procedures regarding the MPS' bidding requirements, conflict of interest, acceptance of gratuities, and disciplinary actions.

California State Auditor's Assessment of 1-Year Status: Fully Implemented


6-Month Agency Response

The organization has established revisions to the policies and procedures in order to enhance vendor selection, and is currently in the process of reviewing the current process in order to ensure that the organization maintain independence in its relationship with vendors.

California State Auditor's Assessment of 6-Month Status: Pending


60-Day Agency Response

The organization has established revisions to the policies and procedures in order to enhance vendor selection, and is currently in the process of reviewing the current process in order to ensure that the organization maintain independence in its relationship with vendors.

California State Auditor's Assessment of 60-Day Status: Pending


All Recommendations in 2014-135R

Agency responses received are posted verbatim.